"Aganneftegasgeologia" is developing the infrastructure of the oilfields of the Nizhnevartovsk Region.

23.07.2010 "Yugra-Inform"

Nizhnevartovsk Region, KhMAO. "Aganneftagasgeologia" has completed construction of high-voltage power line at Yuzhno-Roslavlskoye, Roslavlskoye and Mokhtikovskoye oilfields in Nizhnevartovsk District.

At Roslavlskoye there are built a double-curcuit hgh-voltage  6 kV power line from "Roslavlskoye" substation to well pad No 6, two high-voltage 6 kV lines from "Lesnaya" substation to well pad No 17. To supply power to well pad No 1 of Yuzhno-Roslavlskoye oilfield another high-voltage power line was built. This line helped to replace diesel power with centralized power supply.

The problem of power supply to well pad No 1 at Mokhtikovskoye oilfield was also resolved.

On the whole in the first half of 2010 the subsidiary of "RussNeft" has built more than 14 thousand meters of high voltage lines. Active infrastructure development of the oilfields is going on. At present a high-voltage 6 kV power line is under construction at Yeguriakhskoye oilfield, says the press-servise of the company.

More news

All Show all

RussNeft Announces Support for Regional Social Development

PJSC “RussNeft” continues to assist educational institutions serving children with disabilities.

RussMeft Supports Sports Tournaments in the Regions

PJSC “RussNeft” continues to support regional sports initiatives. In the Khanty-Mansi Autonomous Okrug – Yugra, the Company supported the Open Boxing Championship for the Nizhnevartovsky District Head’s Cup.

RussNeft announces the release of 2,417 sterlet fingerlings into the Volgograd Reservoi

The company's press service has announced the restocking of the Volgograd Reservoir (Volga River), with 2,417 fish fingerlings.